AzMeCo’s first methanol production is scheduled for early 2013, with final commissioning works to be completed in parallel. The initial shipments are expected within the first quarter of 2013. At full capacity, the plant is projected to produce up to 2,000 tons of methanol per day, equating to an annual output of 720,000 tons.
Production at the plant will be based on ICI technology licensed by the British firm Johnson Matthey, and the entire facility will operate with a fully automated control system. Operations will be managed by 24 trained operators, working in three shifts, with six operators per shift. Total investment in the plant’s construction has reached $400 million.